This business case is considering a staged approach to manage increasing traffic demands on the Bruce Highway between Dohles Rocks Road and Anzac Avenue.

First stage – extended north-facing ramps

  • Providing extended north-facing ramps (northbound entry and southbound exit ramps) from Dohles Rocks Road to Anzac Avenue along the Bruce Highway
  • The extended ramps provide an effective additional future lane on the Bruce Highway to the north.

Timing: Finalising business case in late 2022. Construction to start 2024.

See map below.

Future stages – collector-distributor roads to Anzac Avenue

  • Constructing collector-distributor roads on both sides of the Bruce Highway from Dohles Rocks Road to Anzac Avenue
  • Upgrades to the Anzac Avenue interchange to the Bruce Highway
  • A shared pedestrian and cycle path on the east side of the Bruce Highway from Dohles Rocks Road to Anzac Avenue.

Timing: Detailed design and construction timing is not confirmed and is subject to further approvals and funding.

Moreton Connector

The Moreton Connector, a proposed new road east of the Bruce Highway from Dohles Rocks Road to Anzac Avenue, will not progress to design and construction at this stage. The corridor will continue to be preserved by TMR and Moreton Bay Regional Council for future potential use.

View detailed plans for Bruce Highway (Dohles Rocks Road to Anzac Avenue)

To GMBHU project map


Dohles Rocks Road interchange map

The options shown for the upgrades are indicative only and are subject to change following community consultation and as planning progresses.